Pakistan's water ambitions sinking in financial chaos as mega projects face generational delays

SocialTwist Tell-a-Friend    Print this Page   COMMENT

Islamabad | May 16, 2026 4:54:02 PM IST
Pakistan's key water and hydropower projects are slipping deeper into uncertainty as severe funding shortages and soaring construction expenses continue to stall progress on major infrastructure schemes, as reported by Samaa TV.

According to Samaa TV, the documents paint a troubling picture for the country's long-term water security and energy planning. Several flagship projects, once promoted as solutions to Pakistan's growing water and electricity crises, are now expected to take decades and, in some cases, centuries to complete under the existing pace of financial allocations.

Among the most delayed projects is the Dasu Hydropower Project, whose estimated cost has climbed to nearly Rs 1.74 trillion. Officials have warned that if funding continues at current levels, the project could take around 65 years to finish. Authorities have requested Pakistani Rupees (PKR) 145 billion in the upcoming federal budget to keep construction activities moving.

The Diamer-Bhasha Dam is facing a similarly alarming situation. The project's estimated cost has crossed PKR 1.04 trillion, while proposed funding for the next fiscal year stands at just PKR 93.77 billion. Based on the present allocation pattern, the dam may take roughly 46 years to complete.

The Mohmand Dam project is also struggling under mounting financial pressure. Its estimated cost has surpassed PKR 337 billion, and officials say the project could require another 14 years for completion if the government fails to significantly increase funding support. Urban water supply and irrigation schemes are also suffering major setbacks.

The Kachhi Canal Project could reportedly take more than a century to complete, while Karachi's K-IV water supply scheme may need another decade before becoming operational. The K-IV project alone now carries a price tag exceeding PKR 175 billion, as cited by Samaa TV.

Even more concerning are projections linked to smaller infrastructure schemes. Official estimates suggest the Naulong Dam may require 122 years for completion, while the Chashma Right Bank Canal could astonishingly take nearly 1,900 years under the current financing structure.

A separate flood protection programme worth PKR 194 billion may also remain unfinished for centuries, as reported by Samaa TV. (ANI)

 
  LATEST COMMENTS ()
POST YOUR COMMENT
Comments Not Available
 
POST YOUR COMMENT
 
 
TRENDING TOPICS
 
 
CITY NEWS
MORE CITIES
 
 
 
MORE WORLD NEWS
Chile FM's visit imparted fresh impetus ...
US lawmakers press China on Uyghur priso...
PM Modi meets King Willem-Alexander and ...
PM Modi meets King Willem-Alexander and ...
China's expanding maritime tactics raise...
UAE rejects Iran's 'direct involvement' ...
More...
 
INDIA WORLD ASIA
Assam CM inaugurates India's first AI-po...
Tripura's Jampui Hills under Vanghmun PS...
Himachal SEC issues special voting guide...
VHP hails Indore HC Bhojshala verdict, c...
'NTA failed': Congress leader Randeep Su...
Hyderabad: Fire breaks out in Jaipur Exp...
More...    
 
 Top Stories
Aditi Rao Hydari flaunts desi look ... 
Hamas commander behind Oct 7 attack... 
Actor Ram Pothineni turns director ... 
"Remained silent, tolerated everyth... 
Robert Lewandowski announces depart... 
Delhi: American national of Indian ... 
18 Coimbatore students win gold at ... 
IGU Pune: Priya edges out Ojaswini ...