Monitoring committee for Brahmapuram site submits report at Kerala HC, says "There is no equipment for biomining"

   SocialTwist Tell-a-Friend    Print this Page   COMMENT

Kochi (Kerala) | March 14, 2023 11:35:40 PM IST
The monitoring committee inspecting the conditions at the Brahmapuram waste plant, in its report submitted to the Kerala High Court said that there are no adequate facilities for waste management in Brahmapuram.

The monitoring committee which was constituted to inspect the conditions at the Brahmapuram waste plant has submitted its report at the Kerala High Court.

"Not only from Kochi city but also the waste from eight municipalities in the nearby area are brought to Brahmapuram. But there is not even a place to collect this waste. There is no scientific treatment for plastic waste. There is only one shed in the plant. Therefore, the disposal of these wastes is not done properly," the report said.

It further noted that there is no equipment for biomining and it is being done only with a few tools that cannot complete the process on time.

"The amount of organic waste delivered to the plant should be reduced. None of the guidelines issued by the Central Pollution Board for the disposal of stagnant wastes is followed here. The final product after waste treatment is a very poor quality one. The product obtained after normal waste treatment is given to cement companies. But the cement companies are not accepting the product from here as it is of poor quality," the committee submitted in the report.

The committee also apprised the High Court of buildings at the site, saying that the existing building at the site was in a dilapidated state and might collapse at any time.

"Accumulated garbage is likely to flow into the nearby Kadambrayar (river). There are no adequate CCTV systems in the plant. They are needed," it further said.

The monitoring committee has also included new recommendations in the report pointing out the inadequacy of infrastructure in Brahmapuram.

The committee was earlier constituted by the High Court consisting of the Director of Suchitwa Mission, the Chief Engineer of the Local Self Government Department, the District Collector, the Chief Environmental Engineer of the Pollution Control Board, the Corporation Secretary and the Kerala State Legal Services Authority (KELSA) Secretary. (ANI)

 
  LATEST COMMENTS (0)
POST YOUR COMMENT
Comments Not Available
 
POST YOUR COMMENT
 
 
TRENDING TOPICS
 
 
CITY NEWS
MORE CITIES
 
 
INDIA WORLD ASIA
Mumbai Crime Branch recovers evidence ag...
'India is angry at PM Modi's comment...'...
'It makes clear Congress' mindset': BJP'...
'If you are a small shopkeeper, Congress...
Sunetra Pawar gets clean chit in Rs 25,0...
Centre stopped privatisation of Visakhap...
More...    
 
 Top Stories
"I'm able to let go of things": Jac... 
"Shaheen Afridi is a Pakistan legen... 
Congress' Ganesh Godiyal calls PM M... 
Bengaluru Metro Rail Corporation ex... 
IPL 2024: Axar Patel, Rishabh Pant'... 
"Busy auctioning Prime Minister's c... 
Israel rejects reports about discov... 
SC seeks clarification from ECI off...