MMRC completes 97% tunnelling on Colaba-SEEPZ Metro line

   SocialTwist Tell-a-Friend    Print this Page   COMMENT

Mumbai | Thursday, 2021 3:15:05 AM IST
Spelling cheers for Mumbaikars, almost 97 per cent tunnelling work on the longest and fully-underground Colaba-Bandra-SEEPZ Mumbai Metro 3 corridor has been completed with the 39th breakthrough achieved at Mahalaxmi, officials said on Wednesday.

Till date, the Mumbai Metro Rail Corporation (MMRC) Ltd, which is executing the project, has tunnelled 52.60 km of the 54.50 km double line (up/down), marking nearly 97 percent of the total tunnelling work required, company's Managing Director Ranjit Singh Deol said.

The city's first fully subterranean 33.50-kms long Colaba-Bandra-SEEPZ Metro-3 line, which passes below sections off the Mithi River and Mahim Creek, will have 27 stations, including 26 underground, with at least 6 inter-changes at strategic points on the route.

Estimated to cost around Rs 23,136 crore, the entire project is expected to be operational by mid-2022, and transport around 1.60 million commuters daily in full comfort.

In the ongoing work, the latest achievement was the breakthrough at Mahalaxmi Metro Station by the tunnel boring machine Tansa-2, completed in 257 days, using 745 concrete rings, Deol said.

"This was a challenging task as this stretch from the Science Museum Metro Station to Mahalaxmi Metro Station encompasses tunnelling below the buildings which are more than 80 years old and live Western Railway tracks between Mahalaxmi-Lower Parel railway stations," he said.

This work was part of the longest - Package-3 in the total project - which includes Mumbai Central, Mahalaxmi, Science Museum, Acharya Atre Chowk, and Worli metro stations, and has witnessed three major breakthroughs so far.

Officials say that by 2022-end, Mumbai would get at least 3 new Metro lines which will make commuting much easier besides reducing the load on the city roads and the two highways.

Simultaneously, the work on other Metro routes by the Mumbai Metropolitan Region Development Authority is proceeding at full swing in different parts of the city and surroundings.

--IANS qn/vd

( 320 Words)

2021-07-21-21:20:02 (IANS)

 
  LATEST COMMENTS (0)
POST YOUR COMMENT
Comments Not Available
 
POST YOUR COMMENT
 
 
TRENDING TOPICS
 
 
CITY NEWS
MORE CITIES
 
 
 
MORE BUSINESS NEWS
Reinvention of Panchtatva at BURE...
Create an emergency fund with Bajaj Fina...
Spice Grill Flame, a pioneer in the vege...
S&P rates APSEZ's proposed US$750 mi...
India among most promising countries for...
Tata Motors Q1 net loss narrows to Rs 4,...
More...
 
INDIA WORLD ASIA
Jharkhand govt toppling row: Turned down...
Nishank receives 'Maharishi Inter Nation...
Crisis in Chhattisgarh Cong: MLA demands...
Education Minister Dharmendra Pradhan la...
RS likely to see disruptions on Monday o...
UP Covid recovery rate goes up to 99%...
More...    
 
 Top Stories
Lockdown extended again in Kathmand... 
2 numbers used by Bihar Cricket Ass... 
China launches emergency response f... 
Olympics: Nagal goes down to Medved... 
Suspects of attack on ex-Maldivian ... 
Bengaluru 8th in global list of lea... 
Oppn forces second adjournment in R... 
SC slams Gautam Gambhir Foundation,...